Selection framework of disruption analysis methods for megaprojects: an integrated fuzzy multi-criteria decision-making approach


OKUDAN O., Cevikbas M., IŞIK Z.

Engineering, Construction and Architectural Management, 2023 (SCI-Expanded) identifier

  • Yayın Türü: Makale / Tam Makale
  • Basım Tarihi: 2023
  • Doi Numarası: 10.1108/ecam-02-2023-0105
  • Dergi Adı: Engineering, Construction and Architectural Management
  • Derginin Tarandığı İndeksler: Science Citation Index Expanded (SCI-EXPANDED), Social Sciences Citation Index (SSCI), Scopus, ABI/INFORM, Aerospace Database, Business Source Elite, Business Source Premier, Communication Abstracts, ICONDA Bibliographic, Index Islamicus, INSPEC, Metadex, Civil Engineering Abstracts
  • Anahtar Kelimeler: Claim management in built environment, Disruption analysis methods, Disruption management, Fuzzy MCDM, Integrated fuzzy AHP-Fuzzy TOPSIS, Megaprojects
  • Yıldız Teknik Üniversitesi Adresli: Evet

Özet

Purpose: The purpose of this paper is to propose a decision support framework that can be used by decision-makers to identify the most convenient disruption analysis (DA) methods for megaprojects and their stakeholders. Design/methodology/approach: The framework was initially developed by conducting a comprehensive literature review to obtain extensive knowledge about disruption management and megaprojects. Focus group discussion (FGD) sessions with the participation of the construction practitioners were then organized to validate and strengthen the findings of the literature review. Consequently, 17 selection factors were identified and categorized as requirement, ability and outcome. Lastly, the most convenient DA methods for megaprojects were identified by performing integrated fuzzy analytical hierarchy process (AHP) and fuzzy technique for order of preference by similarity to ideal solution (TOPSIS) analysis. Additionally, consistency analysis was also conducted to verify the reliability of the results. Findings: The results revealed that the measured mile method is the most appropriate DA method for megaprojects. In case the measured mile method cannot be adopted due to various technical and contractual reasons, the decision-makers are proposed to consider program analysis, work or trade sampling, earned value analysis and control chart method, respectively. Second, the selection factors such as “Comprehensible analysis procedure,” “Existing knowledge and experience about a particular DA method,” “Ability to resolve greater number of disruption events,” “Ability to resolve complex disruption events,” “Ability to exclude factors that are not under the owner's responsibility” and “General acceptance by practitioners, courts, and arbitration, etc.” were given the top priority by the experts, highlighting the critical aspects of the DA methods. Originality/value: Disruption claims in megaprojects are very critical for the contractors to compensate for the losses stemming from disruption events. Although the effective use of DA methods maximizes the accuracy and reliability of disruption claims, decision-makers can barely implement these methods adequately since past studies neglect to present extensive knowledge about the most convenient DA methods for megaprojects. Thus, developing a decision support framework for the selection of DA methods, this study is the earliest attempt that examines the mechanisms and inherent differences of DA methods. Additionally, owing to the robustness and versatility of this research approach, the research approach could be replicated also for future studies focusing on other project-based industries since disruption is also a challenging issue for many other industries.